The short answer
Progress billing requests payment for contract work completed and eligible materials stored, using an agreed schedule of values. Reconcile each application to prior billings, approved changes, and retainage. QuickBooks can support progress invoicing, but billing, cash collection, and earned revenue remain different measurements.
Founder, Accelerate Business Solutions · Published November 9, 2026 · Last updated November 9, 2026
What progress billing is—and what it is not
Progress billing requests payment as contract work advances, using cumulative completed work and eligible stored materials rather than waiting for final completion. Each application identifies the new amount due after prior billings and retainage. It differs from deposits, milestone billing, and time-and-materials billing; an approved request does not by itself prove earned revenue or collected cash.
Instead of waiting for completion, a contractor submits applications as work advances. Each request shows cumulative value and the new amount due, subject to contract approval. The supporting records explain what changed since the previous application. None of that guarantees immediate payment or proves the same amount is earned revenue.
Deposit
An advance funds work before it is earned. Track it separately from a progress claim and confirm its accounting treatment.
Milestone billing
A contract links invoices to agreed events, such as completing a phase. Evidence of the milestone supports the request.
Time and materials
Billing follows documented hours, materials, and agreed rates. A progress application instead summarizes contract value completed to date.
Build a schedule of values that matches the job
Build a schedule of values from the approved estimate, dividing the contract price into defensible billing lines that reconcile to the contract sum and approved changes. Cross-reference those lines to your cost codes even when the owner's format differs. Avoid front-loading early work: scheduled billing value is not the same as expected job cost.
A schedule of values, or SOV, splits the approved contract price into billing lines. Start with the estimate's work categories and map them to your cost codes. The total scheduled value should reconcile to the contract sum, including approved changes. Keep a documented bridge when the owner's required format groups work differently from your budget.
Use categories the project manager can substantiate. Front-loading too much value into early phases can trigger approval disputes and leave later work underfunded. A billing line is a share of contract price, not necessarily its expected cost. The QuickBooks job-costing guide covers the separate cost structure underneath those lines.
AIA G702/G703 basics without copying the forms
AIA G702 summarizes the payment application, while G703 provides the schedule-of-values detail supporting it. Together they organize contract value, approved changes, completed and stored work, retainage, previous certificates, and current payment due. The American Institute of Architects publishes and licenses these documents; confirm the owner's required format instead of reproducing the forms.
AIA G702/G703 are documents published and licensed by the American Institute of Architects; many owners accept “AIA-style” pay applications. Confirm the required format and licensing. This explanation describes the information, not a reproduction of either document.
G702 is the application and certificate for payment summary: original contract sum, net change orders, completed and stored to date, retainage, previous certificates, and current payment due. G703 is the continuation sheet by SOV line: scheduled value, work completed previously and this period, materials presently stored, total completed and stored, percent complete, balance to finish, and retainage.
| Framing scheduled value | $20,000 |
|---|---|
| Work completed previously | $5,000 |
| Work completed this period | $3,000 |
| Materials presently stored | $2,000 |
| Total completed and stored | $10,000 |
| Complete against this scheduled value | 50% |
| Balance to finish | $10,000 |
| Illustrative agreed retainage amount | $1,000 |
Completed work plus stored materials gives cumulative value. The application summary then deducts agreed retainage and previous certificates to determine current payment due. A prior certificate is not necessarily cash already collected; reconcile receivables separately.
Change orders and stored materials on pay applications
Include change orders on pay applications when approval and contract terms permit, updating contract value and the affected schedule-of-values lines without erasing prior history. Bill stored materials only with the required supporting documents. When materials are installed, move their value into completed work rather than billing twice, and confirm unusual revenue treatment with your CPA.
Keep approval visible
Carry approved change orders into the revised contract value and affected SOV lines. Preserve the original amount, authorization, and previous application history. Proposed or disputed work needs separate tracking; follow the contract before including it in a request.
Support materials not yet installed
Bill stored materials only when contract terms permit, with required supplier invoices, storage evidence, insurance, and ownership documentation. Move their value into completed work when installed instead of billing it again. Eligibility for billing does not alone establish revenue recognition; review unusual stored-material arrangements with your CPA.
Make billing traceable
Doing progress billing in QuickBooks Online
Use QuickBooks Online progress invoicing where your plan supports it: enable the Sales setting, build the estimate, and invoice the approved percentage or amount. On Plus and Advanced, Projects group job activity. Keep retainage separate and reconcile payments. A progress invoice does not automatically satisfy a required pay-application format or calculate WIP revenue.
- 1
Enable progress invoicing
In QuickBooks Online, review Account and settings → Sales and enable progress invoicing where your plan offers it. Check your plan and current interface. Projects are available on QuickBooks Online Plus and Advanced; use the project to keep related estimates, invoices, and job costs together.
- 2
Build the estimate against the project
Use Products/Services that reflect your estimate and cost-code structure. Keep the approved contract and schedule of values alongside it. Customer billing lines may need more detail than the accounting categories; maintain a clear cross-reference rather than assuming they must be identical.
- 3
Invoice the approved progress
Create an invoice from the estimate using a percentage or an amount per line, as the available workflow allows. Distinguish this period's billable amount from cumulative completion. Compare the resulting invoice with the approved pay application before sending or posting it.
- 4
Separate retainage and collections
Where using a manual retainage workflow, a separate item mapped to a retainage receivable account can reduce the amount currently due without reducing earned revenue. Have your bookkeeper verify that setup. Apply the customer's payment to the invoice; do not record the same receipt again as new income.
- 5
Close the month against the WIP
Reconcile gross billings, retained amounts, customer payments, and credits by project. Compare billings with earned revenue using current job-cost estimates. Progress invoices organize billing; they do not automatically calculate percentage-of-completion revenue or the required month-end accounting adjustments.
For the withholding setup, read retainage accounting. Contractors needing structured pay applications may use a field tool such as JobTread; confirm its current pay-application capabilities and the owner's accepted format. Our JobTread QuickBooks integration guide explains the accounting mapping, not a guarantee of document compatibility.
How progress billing drives WIP and over/under billing
Progress billing supplies gross billings to date for the WIP comparison, including withheld retainage rather than just cash collected. Compare billings with earned revenue using current completion and cost estimates. Billings above earned revenue are over-billing, a liability; earned revenue above billings is under-billing, an asset. Reconcile the billing records before reviewing that position.
The WIP schedule compares earned revenue with billings to date. Under the cost-to-cost method, percent complete equals costs to date divided by estimated total job cost; earned revenue equals that completion measure times the contract price. Use current estimates, not just the original bid.
Billings above earned revenue mean over-billing, a liability. Earned revenue above billings means under-billing, an asset. Gross billed work includes retained amounts; cash receipts are not billings. The percentage-of-completion guide and construction accounting overview connect that comparison with the financial statements.
Common progress-billing mistakes
Progress-billing mistakes include unsupported completion, front-loaded values, repeated prior work, unapproved changes, and stored materials counted again when installed. Separate gross billings, retainage, credits, and cash receipts instead of treating the net payment as revenue. Keep application history intact and compare approved billings with current earned revenue and cost-to-complete estimates at month-end.
- Billing from memory. Use an approved schedule of values and supported completion, not a cash target.
- Repeating previous work. Carry forward cumulative history, but request only the new amount due after prior certificates.
- Front-loading values. A large early invoice does not prove early profit; keep values defensible and review remaining work.
- Including unapproved changes. Track proposed changes separately until the contract permits their inclusion.
- Counting stored materials twice. Move value from stored to installed as work progresses; reconcile supplier documentation.
- Treating net payment as revenue. Separate gross work billed, retainage, credits, and cash collected.
- Skipping the WIP review. Approved billings still need comparison with earned revenue and updated cost-to-complete estimates.
The routine matters for home builders, remodelers, and other contractors. Our construction bookkeeping and JobTread bookkeeping pages cover the recordkeeping behind a reliable monthly close.
Progress-billing questions, answered
Progress billing uses an agreed schedule of values to support payment requests as work advances. Contract terms govern approved changes, eligible stored materials, retainage, and documentation. QuickBooks progress invoices can support the accounting workflow where available, but they do not replace required pay applications. Review gross billings separately from cash collection and WIP earned revenue.
What is progress billing in construction?
Progress billing requests payment as contract work advances, usually through a cumulative application supported by a schedule of values. It separates work completed previously, work completed in the current period, and eligible stored materials. The contract controls timing, documentation, and approval. Billing is not the same as collecting cash or recognizing revenue; reconcile those separately so a payment request does not become a misleading profit report.
What is a schedule of values?
A schedule of values divides the contract sum into agreed billing lines, such as site work, framing, and electrical. Each line has a scheduled value and a running record of completion. Build it from the approved estimate and keep a cross-reference to cost codes. It supports the pay application, but it is not a substitute for the job-cost budget or the estimate of remaining costs.
What is the difference between AIA G702 and G703?
G702 summarizes the payment application and certification, including the contract, changes, completed and stored amounts, retainage, prior certificates, and current payment due. G703 provides the supporting schedule-of-values detail by line. These documents are published and licensed by the American Institute of Architects. Many owners accept AIA-style pay applications, but confirm the contract's required format and obtain authorized documents rather than copying a form.
Can QuickBooks Online do progress billing?
QuickBooks Online offers progress invoicing from estimates where supported; check your plan and enable the available Sales setting. On QuickBooks Online Plus and Advanced, use Projects to group job activity. Invoice an approved percentage or amount using the available line options. A progress invoice does not replace an owner's required pay application, nor does it automatically prepare the WIP or recognize percentage-of-completion revenue.
How do change orders affect a pay application?
Approved changes adjust the contract sum and the relevant schedule-of-values lines, with a clear record of authorization. Keep proposed, disputed, and approved changes distinguishable. Carry the revised values through the current application and future periods without erasing previously approved history. Follow the contract's rules for when change work can be billed, and keep its costs assigned to the job while approval or payment remains unresolved.
How does progress billing affect a WIP schedule?
Progress billing supplies billings to date; the WIP compares that amount with earned revenue based on the current completion method and cost estimates. Billings above earned revenue are over-billing, a liability. Earned revenue above billings is under-billing, an asset. Include gross billed work, including withheld retainage, rather than only cash received. Confirm the revenue method and financial-statement presentation with your CPA.
Keep reading:
- Retainage accounting — separate earned value from amounts withheld.
- The WIP schedule — read each job's over/under billing position.
- Percentage of completion accounting — the cost-to-cost calculation behind earned revenue.
- Job costing in QuickBooks Online — projects, items, costs, and monthly reports.
- JobTread QuickBooks integration — keep field records and accounting mappings aligned.
- Construction bookkeeping — the daily records that support billing and closeout.
- Construction accounting — connect project activity with financial statements.
Retainage rules depend on the contract and state law. Confirm tax and revenue treatment with your CPA; billing approval and cash collection do not determine the accounting method.

About the author
Shannon Price
Founder, Accelerate Business Solutions
Shannon has spent 10+ years inside the books of small businesses and runs every client relationship personally. Most of her work is with contractors, JobTread users and independent insurance agencies.
More about ShannonGet billing and job costs telling the same story.
Bring your estimate, a recent pay application, and your QuickBooks questions. Let's talk through the records needed for clear billing and a dependable monthly close.
Book your free consult